Default Pouring the suspended slab and core fillinh at the same time?

Without a cement mixer im going to get a truck of premix in. I am considering building the base with hollow concret blocks then framing the suspended slab and pouring that as well as filling the cores at the same time. Has this been done? I was thinking i could use a construction glue to hold the blocks in place for the pour.
Reply With Quote
  #2  
Old 08-30-2009, 09:55 AM
Neil2's Avatar
Il Pizzaiolo
 
Join Date: Oct 2006
Location: Vancouver Island
Posts: 1,374
Default Re: Pouring the suspended slab and core fillinh at the same time?

You can do it in one pour. In fact this will be slightly stronger that two separate pours.

If you are careful during the pour, the blocks should hold together well enough by gravity. If you want to be sure, mortar the blocks. The mortar is probably cheaper than construction adhesive.
Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On



All times are GMT -7. The time now is 01:04 AM.

Powered by vBulletin® Copyright ©2000 - 2014, Jelsoft Enterprises Ltd.
Search Engine Friendly URLs by vBSEO 3.6.0
2006/10 Forno Bravo, LLC