I need some quick advice...

I was planning to buy the vermiculite today for my vermicrete layer so that tomorrow I could pour the 10cm of concrete slab and then the 10cm of vermicrete before the concrete set.

That said, the supplier I found (11 /100l bag) wont let me collect after 15:30 - and I got there at 15:31 (pain in the @ss I know...)

So - can I pour the concrete and vermicrete layers separately? What is the risk of doing this? Or should I delay pouring the concrete until I can pour the vermicrete as well?

M.
Reply With Quote
  #2  
Old 08-03-2012, 09:10 AM
Tscarborough's Avatar
Il Pizzaiolo
 
Join Date: Oct 2009
Location: Ausitn
Posts: 3,128
Default Re: Vermicrete Layer Advice

You do not normally do them both at the same time anyway.
Reply With Quote
  #3  
Old 08-03-2012, 09:46 AM
Laborer
 
Join Date: Jun 2012
Location: London, UK
Posts: 90
Default Re: Vermicrete Layer Advice

Great - thanks! I was worried that if the two layers weren't bonded together, bad things would happen

M.
Reply With Quote
  #4  
Old 08-03-2012, 03:14 PM
david s's Avatar
Il Pizzaiolo
 
Join Date: Mar 2007
Location: Townsville, Nth Queensland,Australia
Posts: 4,854
Default Re: Vermicrete Layer Advice

Because the vermicrete layer contains so much water it is advisable to leave it as long as possible (a few weeks if you can bear to wait that long) to allow it to dry before building over it and trapping the moisture it contains.
Reply With Quote
  #5  
Old 08-03-2012, 03:53 PM
Tscarborough's Avatar
Il Pizzaiolo
 
Join Date: Oct 2009
Location: Ausitn
Posts: 3,128
Default Re: Vermicrete Layer Advice

I haven't used vermiculite, but using perlite at the recommended water ratio, it is pretty dry. For a 4-1 mix using 4cuft perlite, 1 cuft portland, and 10 gallons of water, most of the water will be used in hydration of the cement and unless you want to there is no reason to wait more than a day or 2 to build over it.

http://www.perlite.org/perlite_info/...e_concrete.pdf
Reply With Quote
  #6  
Old 08-03-2012, 03:59 PM
Neil2's Avatar
Il Pizzaiolo
 
Join Date: Oct 2006
Location: Vancouver Island
Posts: 1,374
Default Re: Vermicrete Layer Advice

"You do not normally do them both at the same time anyway."

Particularity since the insulation layer has a different "footprint" than the slab. The insulation layer should only be under the hearth bricks and dome bricks. You have to set up new forms on the recently poured slab surface.

If the insulation layer extends to the edge of the suspended slab, you will have created a very broad entryway for moisture.

On that note, make sure the surface of your structural slab has positive drainage and that there are no low spots or "bathtubs" to hold water. If you haven't sloped your slab you may have to do some grinding at this point.

Keep both the slab and the vermicrete layer well supplied with water = permanently damp, for at least 7 days. (You can start build on either layer within a few days). I do not share David's concern with trapping water. I think a properly cured concrete/vermicrete layer is more important. Add lots of water.

Last edited by Neil2; 08-03-2012 at 04:06 PM.
Reply With Quote
  #7  
Old 08-03-2012, 04:29 PM
david s's Avatar
Il Pizzaiolo
 
Join Date: Mar 2007
Location: Townsville, Nth Queensland,Australia
Posts: 4,854
Default Re: Vermicrete Layer Advice

Quote:
Originally Posted by Tscarborough View Post
I haven't used vermiculite, but using perlite at the recommended water ratio, it is pretty dry. For a 4-1 mix using 4cuft perlite, 1 cuft portland, and 10 gallons of water, most of the water will be used in hydration of the cement and unless you want to there is no reason to wait more than a day or 2 to build over it.

http://www.perlite.org/perlite_info/...e_concrete.pdf
Approximately one third of the volume of vermiculite or perlite of water is required to make a vermicrete or perlcrete slab. The water does not disappear when hydration takes place. It does not magically get lighter(this can be tested by weighing a sample as it dries to calculate water loss) sure you can build over it the next day, but this does make the water removal more difficult later.
I often weigh castings to calculate water loss, it is quite an accurate measure if you know the weight ofbthe dry casting
Reply With Quote
  #8  
Old 08-03-2012, 04:32 PM
Tscarborough's Avatar
Il Pizzaiolo
 
Join Date: Oct 2009
Location: Ausitn
Posts: 3,128
Default Re: Vermicrete Layer Advice

It doesn't disappear, it is incorporated into the crystalline structure of the paste.
Reply With Quote
  #9  
Old 08-03-2012, 04:45 PM
david s's Avatar
Il Pizzaiolo
 
Join Date: Mar 2007
Location: Townsville, Nth Queensland,Australia
Posts: 4,854
Default Re: Vermicrete Layer Advice

When making vermicrete or perlcrete you require about double the content of water that you would normally use in a regular concrete mix. Given that a regular concrete slab still contains a fair proportion of mechanical water that eventually escapes to the atmosphere a vermicrete slab has proportionally a huge amount to be removed. This can easily be demonstrated by making a test slab and weighing the dry ingredients including the water, then weighing the slab daily to calculate the water loss over time. If I have time I'll do it and graph the results for you.
Reply With Quote
  #10  
Old 08-04-2012, 07:44 AM
Laborer
 
Join Date: Jun 2012
Location: London, UK
Posts: 90
Default Re: Vermicrete Layer Advice

Interesting. Slab laid (it's still wet, so I could theoretically give it a positive slope) - but my query is why does it need a slope?

It'll all be encased in a large brick house - I agree that there will be some steam - but why would the water condense under the vermicrete layer?

Just curious...

M.
Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Vermicrete or Perlcrete as last layer mrchipster Tools, Tips and Techniques 13 05-06-2014 05:21 AM
Newbie seeking advice for hybrid oven... Satan Newbie Forum 11 05-01-2012 10:04 PM
Insulating hearth - Use firebricks instead of vermicrete? brennerwilliam Newbie Forum 2 09-20-2011 12:08 AM
Using hardibacker as vermicrete form kebwi Tools, Tips and Techniques 4 02-09-2010 09:52 AM
stucco advice mieno Getting Started 23 03-20-2008 07:59 PM