| I'm up to the fifth chain above the soldiers on my 42" oven, and the way things worked out this chain would naturally touch (barely) above the top of the 12" arch bricks. I'm thinking I may have positioned my inner arch too far out from the center of the oven, as it doesn't appear that there will be anything to support those bricks from underneath that would come together over the arch. I can cut some so that the back of the brick is flush with the vertical surface of the arch, but even with a really strong mortar bond it doesn't seem (to an amateur mason) that that would be a good decision to have the following chains resting on these 'floating' bricks. Any suggestions as to how others have handled this? Do you just trust the mortar? |
|
#2
| ||||
| ||||
| If I read it correctly, simply make the following couple of chains more egg shaped to get some lip on the arch and then gradually bring them back round as you proceed (technically you are corbelling them).
__________________ To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts. |
|
#3
| |||
| |||
| You did - and thank you very much for the reply. I went back out and noodled on it a bit, and after reviewing some pictures I ground off a little resting place in the arch for the brick in question. That means it would bond to the adjacent (supported) brick, and would have a small (maybe 5% of the bottom of the brick) bearing surface on the angled top of the chain. The brick directly above the top of the arch would be slightly better, maybe 10% bearing surface. Is that approach, and filling the wedge gap beneath with mortar and / or brick triangles asking for disaster? I noticed that I was naturally corbelling (that is a new word for me - thanks!) the first and second chain, and started on the third to try to 'catch up' to what my indispensable tool was telling me was the 'correct' shape. Thanks again... |
|
#4
| ||||
| ||||
| After you close the hole at top it is not an issue. Until then you may want to build some falsework under it if you are at less than about 40% of the brick supported.
__________________ To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts. |
|
#5
| |||
| |||
| I had a heck of a time with that part of the dome. Once it got it in place and the Mortar was dry it felt quite solid.
__________________ WCD My slow journey to pizza. To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts. |
|
#6
| ||||
| ||||
| Quote:
I should be dropping in my keystone this week some time! ~Bob
__________________ My Oven Progress: To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts. If you fail to plan, you plan to fail! |
|
#7
| ||||
| ||||
| Without a doubt, that's the hardest part of the dome. I found myself sitting inside the partly built dome looking at the transition into the arch and thinking about it for quite a while. Once the mortar cures, it will be fine.
__________________ Joe Member WFOAMBA Wood Fired Oven Amatueur Masons Builders America My thread: To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts. |
|
#8
| |||
| |||
| Thank you all for your replies. I have achieved a level of Zen like calm about it. My solution was to use an entire brick across that part of the dome, and rather than 'hanging' the brick as I've seen a few others do, I used a grinder and made an indentation on the back side of the arch. If I hung the brick, the portion that made it over the dome would be a little to thin and shallow for my taste. In addition, I set the brick back slightly (about 1") from the two adjacent bricks to give it a little more of a safety net. It feels very sturdy now. I can relate to the sitting and staring comment, I was in there for quite a while just cogitating. I got back to it yesterday ready to put up the 6th chain and the head broke off of my indispensible tool within 30 seconds of starting. It was affixed with JB weld, I guess there is a vote for using an actual weld to hold it on. I repaired it yesterday and hopefully today will make some progress.. Thanks again! |
![]() |
| Thread Tools | |
| Display Modes | |
| |
Similar Threads | ||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| High Heat Mortar Primer | james | Getting Started | 75 | 08-27-2011 09:12 AM |
| What is the best oven mortar mixture for the bricks in the dome? | shingletown paul | Newbie Forum | 0 | 11-30-2009 03:17 PM |
| How thick a mortar gap with "horizontal" soldiers? | kebwi | Tools, Tips and Techniques | 6 | 11-05-2009 09:02 AM |
| Maximum mortar joint on inner oven surface? | kebwi | Pompeii Oven Construction | 17 | 10-27-2009 07:11 PM |
| Fire Mortar vs. Refax Refractory Mortar | southpaw | Pompeii Oven Construction | 4 | 04-07-2007 06:02 AM |