| I am in the planning phase of my Pompeii project. I'd like some info regarding the average hours involved from start of construction to completion - not including exterior finish work. I am a DIY'er with average masonry experience. Thanks very much. |
|
#2
| ||||
| ||||
| Did anyone count? The problem with this question is that everyone's oven is different, and most of us are squeezing a few hours out between weekend errands. |
|
#3
| ||||
| ||||
| You got that right Dave! After work last night, while I was putting down pavers, I was thinking about my oven - does that count as time spent? |
|
#4
| ||||
| ||||
| Brian, great question, but really hard to answer. I started excavation in May last year, and was pretty well done by August. No idea how many hours. These usually are built along with other yard changes - we placed pavers also, which took some of the time, as did some of my landscaping. I still have some brickwork to do on the fascia of the base, as well as grinding my concrete countertop and making a fireplace to extend the patio season. The design style (especially the enclosure) determine this. The foundation, stand, and dome were pretty quick, probably finished within a month (just with the free time I could come up with). If I include time researching and learning about these the oven on this website it probably doubles. |
|
#5
| ||||
| ||||
| Agreed. There is calendar time, and then there are man hours. My first oven was interrupted by a house extension, so it was left untouched for months. I didn't count hours -- I think I was afraid to. I was completely inexperienced with masonry, so even the basics of the foundation and the stand were a big learning curve. I think everyone would agree how important the learning curve is, and how much faster a second oven would go compared with the first. James
__________________ To view links or images in signatures your post count must be 5 or greater. You currently have 0 posts. To view links or images in signatures your post count must be 5 or greater. You currently have 0 posts. |
|
#6
| |||
| |||
| Folks - Thanks for the feedback. I am just looking for a rough estimate man hours. I'm in the same situation as I am building a flagstone patio as part of this project. I am taking before pictures now so I can document the whole project. Another area where I am a little confused is related to venting. The instructions suggest a rectangular clay refractory liner as an alternative. Where would I purchase a liner? Do most masonry supply companies sell these liners? Is there an online site you recommend? Thanks again for the support! |
|
#7
| ||||
| ||||
| This is the stuff - 8 inch square refractory flue tile: ![]() Shown here sitting on top of my home made funnel, made of bigger pieces of the same stuff. It's heavy and fragile. Not a good combination for mail order. Try to find it locally. |
| Thread Tools | |
| Display Modes | |
| |
| | ||||
| Thread | Thread Starter | Forum | Replies | Last Post |
| Le Panyol construction and Stability | MAINEWOODHEAT | Getting Started | 8 | 02-15-2007 09:22 PM |
| Hearth and Dome construction questions | asparapani | Pompeii Oven Construction | 13 | 11-21-2006 12:51 PM |
| Radial Oven Construction | armac | Pompeii Oven Construction | 4 | 08-04-2006 04:16 AM |
| dome construction | mario | Pompeii Oven Construction | 9 | 04-17-2006 08:49 PM |
| Construction Timeline | wvachuska | Getting Started | 3 | 02-20-2006 11:09 PM |