#1  
Old 01-19-2009, 11:53 AM
Laborer
 
Join Date: Dec 2008
Location: Northern California
Posts: 94
Default Mason says 30 day cure?

The mason building my oven says it should cure 30 days before I heat it up. I did a search here, and see 7 days as an average.

Anyone think it should be longer than the 7 days?

Thanks,
Ellie
Reply With Quote
  #2  
Old 01-19-2009, 10:12 PM
Jed Jed is offline
Journeyman
 
Join Date: Apr 2008
Location: Bend, Oregon; West Coast USA
Posts: 428
Default Re: Mason says 30 day cure?

Ellie,

The only cement that will be effected by the curing fires is the cement used in the 'high heat mortar' used to place the fire brick in the dome. All of the other cement products are effectively protected from the heat of the fire by the insulation.

The books will say that cement in the mortar will reach nearly full strength in 28 days (for this conversation - the same as 30 days) after mixing and placing. The cement in the concrete (or mortar) chemically reacts with the water, it turns the powder cement (and sand and what ever) to a solid material. The reaction is slow. Most of the 'curing' happens at the first part of the cycle, and the rate of 'curing' slows over time. Over the course of the 28 day cycle, the largest part of the reaction is complete. At 28 days, you can make assumptions about the maximum strength of your mortar.

I expect your mason is referencing this part of the puzzle, the curing cycle of the cement in the masonry.

When you start your curing fires, you will essentially stop the chemical reaction in the cement (now mortar). The cement needs water to do it's magic (powder to solid). The curing fires will drive the moisture from the mortar, and you will not allow the mortar to achieve it's full maximum strength.

The choice most of us make is that after about a week, the mortar is strong enough. The design of the dome in the Pompeii is an arch, in three dimensions not just two dimensions. The choice is to let the mortar cure fully or decide that good enough is good enough, and because it is a dome / arch structure, it isn't going anyplace... and the mortar doesn't need it's full strength to be 'good enough'.

So, it will be your choice.

It is correct that you should let the mortar cure fully, but my dome didn't fall down because I started my curing fires after about two weeks.

I was glad to see the form on your base changed to keep the concrete continuous.. Is your plan to have a 6 inch thick pad to as a base for your structure?

See you,

JED
Reply With Quote
  #3  
Old 01-19-2009, 11:06 PM
Les's Avatar
Les Les is offline
Il Pizzaiolo
 
Join Date: Sep 2005
Location: Carson City, NV
Posts: 2,862
Default Re: Mason says 30 day cure?

Ellie,

I think your mason is stating rule of thumb. Concrete takes forever to fully cure. I recall reading that the "mud" used to make the Hoover dam is still in the process - could be folklore, don't know. You are just trying to avoid the proverbial cracks - almost impossible. David let his oven naturally hydrate for months - still got cracks. I used next to nothing for mortar - still got cracks. I say let it dry for a week, bring little fires to big, after a week, call it done. Just my opinion (but I respect it )

Les...
__________________
Check out my pictures here:

To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts.


If at first you don't succeed... Skydiving isn't for you.
Reply With Quote
  #4  
Old 01-20-2009, 12:40 AM
Il Pizzaiolo
 
Join Date: Dec 2006
Location: Mishigame & Iberia
Posts: 1,168
Default Re: Mason says 30 day cure?

Good discussion Jed ... the natural curing gives off heat so adding heat drives the reaction the wrong way.

The mantra from me is "the longer the better" as you can't wait too long but you can certainly get them started too early.

but you get so damned excited with these WFO, you want to see them going!

....and cracks happen....everybody has one!
__________________

To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts.
Tiempo para guzarlos.....
To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts.
...enjoy every sandwich!
Reply With Quote
  #5  
Old 01-20-2009, 02:16 AM
nissanneill's Avatar
Il Pizzaiolo
 
Join Date: Apr 2007
Location: Adelaide, South Australia
Posts: 1,877
Thumbs up Re: Mason says 30 day cure?

Ellie,
are you planning on using high temperature refractory adhesives (mortar) or the 'poor mans' 1pt hydrated lime : 1 pt portland cement : 1 pt fireclay : 3 pts brickies sand as your mortar?
I used the latter, commenced my drying fires as soon as I applied the outer insulation and had 4 fires and I HAVE NO CRACKS!!!! Anyone is welcome to come to check. Check with Tim and Benny who have inspected it lately quite closely! Benny also took several pics inside the dome only last Friday!
So, my advice is to follow my build BUT don't go stupid with your fires and get it dried and used as soon as practicable!

Cheers.

Neill
__________________
Prevention is better than cure, - do it right the first time!

The more I learn, the more I realise how little I know


Neillís Pompeiii #1

To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts.

Neillís kitchen underway

To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts.
Reply With Quote
  #6  
Old 01-20-2009, 05:16 AM
dmun's Avatar
Moderator
 
Join Date: Jul 2005
Location: New Jersey USA
Posts: 4,216
Default Re: Mason says 30 day cure?

Because of winter, and the construction of an overly ambitious chimney, my oven sat fully six months before I started the curing fires. I pretty much got the same cracks as everyone else.
__________________
My geodesic oven project:
To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts.
,
To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts.
Reply With Quote
  #7  
Old 01-20-2009, 10:50 AM
Laborer
 
Join Date: Dec 2008
Location: Northern California
Posts: 94
Default Re: Mason says 30 day cure?

Well, this is a most informative discussion. I really appreciate your teaching on this one.

I do have the time to wait the month if it needs it.. though, it looks as though if I really want to use it and have some fun, two weeks is the average time. Is that correct?

I don't know which mortar he is going to use for the fire brick. I will ask him tomorrow morning. I did wonder that myself. I did not notice any lime in the materials list though. Hmmm, wonder what he is going to use? He is used to doing fireplaces but has never done a wfo before.

Ellie
Reply With Quote
  #8  
Old 01-20-2009, 04:49 PM
Laborer
 
Join Date: Oct 2008
Location: Australia
Posts: 62
Default Re: Mason says 30 day cure?

Make sure he is using refractory mortar, not just ordinary sand/cement.
Reply With Quote
  #9  
Old 01-20-2009, 05:12 PM
Laborer
 
Join Date: Dec 2008
Location: Northern California
Posts: 94
Default Re: Mason says 30 day cure?

Thanks, Glenn. . Refractory mortar is the fire clay mixture that is in the plans and on the forum, right? Will he use it on the floor and dome?

Thank you,
Ellie

Last edited by Ellie; 01-25-2009 at 11:53 AM. Reason: Correction
Reply With Quote
  #10  
Old 01-20-2009, 05:40 PM
dmun's Avatar
Moderator
 
Join Date: Jul 2005
Location: New Jersey USA
Posts: 4,216
Default Re: Mason says 30 day cure?

Quote:
Refractory mortar is the fire clay and lime mixture that is in the plans and on the forum, right?
That mixture works fine, but a mason who's used to building fireplaces will probably want to use a commercial refractory mortar like Heat-stop.
__________________
My geodesic oven project:
To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts.
,
To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts.
Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Anxious to cure - is it time? Valan Pompeii Oven Construction 0 11-07-2008 12:22 PM
cure questions waynebergman Firing Your Oven 11 05-07-2008 05:09 AM
HELP! Can I cure and test oven before enclosing? Nick Pompeii Oven Construction 25 10-21-2007 03:41 PM
Cure before insulating? whocanitbenow Pompeii Oven Construction 4 04-27-2007 05:04 AM
Time to cure hearth Jack Chastain Getting Started 3 10-20-2006 06:25 AM


All times are GMT -7. The time now is 01:06 AM.

Powered by vBulletin® Copyright ©2000 - 2014, Jelsoft Enterprises Ltd.
Search Engine Friendly URLs by vBSEO 3.6.0
© 2006/10 Forno Bravo, LLC