#1  
Old 01-04-2007, 11:44 AM
Serf
 
Join Date: Dec 2006
Location: Mill Valley, Ca 94941
Posts: 8
Default Just getting started

I'm building a 72x88" stand for a 42" pompeii oven, do I need a center support for the concrete harth?
I have read someplace to add lime to the vermiculite portland insulation mixture?
Is there any good source for firebricks in Marin-Sonoma County, the oven is being build in Sebastopol and I live in Marin.
Any input is very much appreciated
Thank you Rudi
Reply With Quote
  #2  
Old 01-04-2007, 01:43 PM
dmun's Avatar
Moderator
 
Join Date: Jul 2005
Location: New Jersey USA
Posts: 4,216
Default Re: Just getting started

It doesn't hurt to put a center support in your slab forms, because as the plywood form absorbs moisture it can sag. You want that thing rigid while for the week it cures. It's a lot of weight.

Any masonry supply can sell you firebricks. In a busy area like Marin county there will be be multiple suppliers: shop around for the best price. For ordinary firebricks you want to go to a stone yard or building supply, the refractory dealers will most likely sell you a better (and more expensive) grade of brick than you need.

Good luck with your project.
Reply With Quote
  #3  
Old 01-06-2007, 09:53 AM
james's Avatar
Brick Oven Merchant
 
Join Date: Mar 2005
Location: Pebble Beach, CA
Posts: 4,648
Default Re: Just getting started

Welcome aboard Rudi,

We're just up the road in Healdsburg (at least when we are there) and I like SBI in Windsor -- they have just about everything. They also have a Forno Bravo oven on display and are going to be installing a live demo oven this spring. Still, Windsor might be a little far.

If you find a good Marin source let us know and we can add it to the forum. You are in a great spot for a brick oven.
James
__________________

To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts.


To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts.
Reply With Quote
  #4  
Old 01-09-2007, 09:48 AM
Serf
 
Join Date: Dec 2006
Location: Mill Valley, Ca 94941
Posts: 8
Default Re: Just getting started

Thank you very much for your input, I finished the stand and harth this weekend. I used 8x8x16 bondbeams with a cont. #4 horizontal rebar at the bottom and top course. I used mortar for the blocks, added a rebar every second hole and backfilled all with concrete. I used Vermiculite instead of Perlite, since the Perlite at the Homedepot was to powdery. Mixing the vermiculite was easier than I thought. I also build a BBQ/Smoke house Base by addind a 4x4 foot section to the harthstand. This week I will be looking for firebricks. At Friedmans in Santa Rosa they have a Firebrick 4 1/2 x2 1/2 x9 . I wonder if I can use this one. They want $1.49 and the weight is about 8 Pounds. At Shamrock in San Rafael they they tried to sell the more expensive one since the lower priced one can only be used up to 1200 degrees. Any input on this available?
thanks
Rudi
Reply With Quote
  #5  
Old 01-10-2007, 01:01 PM
Peasant
 
Join Date: Nov 2006
Location: woodmere NY 11598
Posts: 43
Default Re: Just getting started

Hey Rudi, taht sounds like the brick I used and they are fine Low duty fire brick, I soaked all the bricks in a bucket they absorb the water rather quickley, I got about 5 in a bucket at a time, I used 165 bricks for the entire 36" oven including the floor, I used a skill saw with a masonery blade set at 1/4 " depth scored each brick and then fliped them over and hit the opposit side of the score with a brick hammer I was done in 2to 3 hours. hope this helps you.
Reply With Quote
  #6  
Old 01-16-2007, 07:23 PM
Serf
 
Join Date: Dec 2006
Location: Mill Valley, Ca 94941
Posts: 8
Default Re: Just getting started

I appreciated all the input that I received from: dmun, James and Captain.I cut all the bricks today and did a trial layout.While I was laying out the dome I've run into a problem. It's a low vault 42" dome, 18" interior height. Laying the bricks along the drawn line, I averaged appr. 3/8" outside gap on all bricks except between the 1st and 2nd row, where the bricks sit on the narrow 2 1/2" side and the 2nd row sits on the 4 1/2" side I've got a 2" gap on both sides. Am I doing something wrong or do I need to cut a 2" angle off the bottom on the 1st row? Or do I have to cut a 2" angled shim to insert? What is the best way to solve this? Also is the 3/8" gap on the other bricks acceptable?


Thanks in advance.

Rudi
Reply With Quote
  #7  
Old 01-17-2007, 08:50 AM
jengineer's Avatar
Master Builder
 
Join Date: Aug 2005
Location: Garden-A, South California
Posts: 572
Default Re: Just getting started

The brick surfaces that face the inside of the oven should be set as close as possible to each other, you may get a gap of 1l8 to 3/8 thick that is filled with fireclay mortar. The surfaces that face the outside will have gaps that are filled with fireclay mortar that can be quite large because you are building a circular structure with linear material. You are putting in a square when a pie or a V would be more suitable. The key here is to make the fire side surfaces as close as possible.

The first course is sometimes called a soldier course. If your gap is too biug due to the making of a perfect circle you could decrease the over all gaps by slicing a brick in half lengthwise. This filler brick should be put toward the side so that it is hard to see when someone looks into the oven from the opening.

On top of the first course can be called the first ring. this ring of bricks generally will have the most filler mortar applied as it sets the angles for the dome. Persnally I have not been too thrilled with how this first ring is placed. The fire side of the bricks looks good but below each brick and on each side of the brick is a lot of mortar. There is not much you can do about the sides as again our bricks are not wedge shaped and thus you use the fireclay mortar.

Here is a dry shot of the gaps you can expect on the outside of the dome, thanks to marcel

http://i14.photobucket.com/albums/a3...d1stcourse.jpg


One thing to rememeber is that the instructions are made so that the every day home owner can build a pizza oven without too much engineering and a modicum of skill.

A professional brick layer, and yes we have a few everyday homeowners here who have uncovered a hidden skill, would do something like the folks at The Masonary Heater Association would do <giving credit where credit is du>, make the first ring on top of the soldier course a skrew course. That involves cutting your bricks at the angle that will be set up for the rest of the rings.

.
http://mha-net.org/graphics/wild06/oven/oven20.jpg

The idea is to get the fire side bricks as tight as possible. Here is a shot from Paulages.

http://i11.photobucket.com/albums/a1...s/DSC01827.jpg


Paul then went back inside the oven and back-filled or buttered in with mortar all the gaps that are visible.

I hope this helped

je

p.s. go into your profile and change your location. Although it is nice you really do not want to be broadcasting your actual physical address to the world.

Last edited by jengineer; 01-18-2007 at 08:30 AM. Reason: correcting bad typing
Reply With Quote
  #8  
Old 01-17-2007, 07:50 PM
Serf
 
Join Date: Dec 2006
Location: Mill Valley, Ca 94941
Posts: 8
Default Re: Just getting started

Thank you very much je.
Your input helped. That means the so called soldiercourse sits straight on its 2 1/2" side and the next course will be angled to fit the dome curve even if one has to fill the 2" gap with mortar or cut pie shaped bricks to compensate.

Thanks again je
Rudi
Reply With Quote
  #9  
Old 01-18-2007, 12:22 PM
DrakeRemoray's Avatar
Il Pizzaiolo
 
Join Date: Mar 2006
Location: Littleton, CO
Posts: 1,211
Default Re: Just getting started

I started angling in on course 4, Course 1 was a soilder course, then 2 and 3 sat on the flat sides. I don't think most do it that way, but anyway...

to your question about the angle. I think this picture shows using a lot of mortar to get the first leaning course to fit the curve of the dome. Hope this helps.



Drake
Reply With Quote
  #10  
Old 01-22-2007, 08:33 PM
Serf
 
Join Date: Dec 2006
Location: Mill Valley, Ca 94941
Posts: 8
Default Re: Just getting started

Thank you very much Drake, the pic is a big help. I have some other questions though, some of the bricks that I bought have some minor cracks in them, are they ok to use or should I just toss them? My other question is would it be better to cut the floor of the pizza oven round and set the soldier course on top of the insulation next to the floor and cut the soldier bricks 7" tall? or is it better to let them sit on top of the floor with the 4 1/2" height?


are there any thoughts on this?



Thanks again,

Rudi
Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Getting Started Ryan Pompeii Oven Construction 1 07-14-2006 10:10 AM
Getting started! Help! Marcel?? intheberkshires Newbie Forum 2 03-11-2006 12:02 PM
Getting started questions mnreeder Getting Started 7 02-24-2006 11:33 AM
New Oven Started svtlightning Brick Oven Photos 10 08-01-2005 02:30 AM
New Pompeii Started Keith Oertli Pompeii Oven Construction 15 06-28-2005 07:00 AM