I poured a 6" Foundation slab and I'm wondering how long I should wait to take off the forms and how long before I can start stacking my cement block for the stand?

It's been a couple days and seems pretty firm but I worry I'll put too much on too quickly and strain anything still too wet lower down.

Thanks,
Shay
__________________
Shay - Centerville, MN


To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts.
Reply With Quote
  #2  
Old 06-22-2009, 09:48 AM
Master Builder
 
Join Date: Mar 2008
Location: Washington State USA
Posts: 777
Default Re: Foundation Drying question

Shay,
Concrete cures by a chemical reaction not by drying. Drying however, can retard the curing and lower the ultimate strength of the concrete. Concrete likes/needs to be kept wet/damp for several days after being poured. When I poured the slab for my house I nailed thin strips on top of the forms and "ponded" the whole slab (28x40ft) for a week which was way overkill, but it was summer and hot. On my slab/foundation for the WFO I covered the surface with old towels and wet them down with a hose several times a day for the first few days.

Concrete will continue to cure and get stonger for decades, however, for all practical purposes concrete will have over 90 % of it's final strength in 28 days. It's not uncommon to pull the forms in three days and have the concrete strong enough to have workmen start to install sill plates within a week. The surface will be somewhat delicate and should you have a fancy ultra smooth finish you want to be careful as it can be fairly easily damaged for the first week.
Hope this is some help,
Wiley
Reply With Quote
  #3  
Old 06-22-2009, 10:22 AM
blacknoir's Avatar
Apprentice
 
Join Date: Jun 2009
Location: Minnesota
Posts: 243
Default Re: Foundation Drying question

Kinda. You guys and your specifics. I have been keeping it wet but I do not have a ultra smooth finish because I didn't care that much for this part. I'll keep wetting it down and probably start stacking this evening. I poured Saturday morning so that's almost 3 days.
__________________
Shay - Centerville, MN


To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts.
Reply With Quote
  #4  
Old 06-22-2009, 04:30 PM
Neil2's Avatar
Il Pizzaiolo
 
Join Date: Oct 2006
Location: Vancouver Island
Posts: 1,374
Default Re: Foundation Drying question

Keep it damp for at least 6 days. Longer if possible.

Concrete generally reaches 50% of its ultimate strength after 6 days and as Whiley notes, 90% after 28 days. (but only if it has moisture available continually for the entire period.)

You should be OK to start build the block walls after 3 days of curing.

Last edited by Neil2; 06-22-2009 at 04:37 PM.
Reply With Quote
  #5  
Old 06-22-2009, 07:51 PM
tony boca's Avatar
Laborer
 
Join Date: May 2009
Location: Boca Raton, Florida
Posts: 74
Default Re: Foundation Drying question

I poured my 6-8" foundation on saturday evening and pulled the forms today which is 2 full days. I'll let you know if iI have any surprises.
__________________
Cheers!
Tony

See My Photos:
To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts.


My thread:

To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts.
Reply With Quote
  #6  
Old 06-23-2009, 04:49 AM
Serf
 
Join Date: May 2009
Location: Raleigh
Posts: 10
Default Re: Foundation Drying question

I laid the first course of blocks while the slab was still wet (3-4 hours after the pour), and built the rest of the stand the next morning. Also, it is probably best to brush the slab to make it rough. You don't really want the slab too smooth, otherwise you won't get good bonding of the stand to the slab. If you are worried about that, they sell concrete bonding agent at home depot which should do the trick.

Your mix was probably 3000 or 4000 psi, so I wouldn't worry... Just keep off the edges.

--J
Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Brick Oven Foundation Question roundmanone Newbie Forum 11 03-14-2009 10:12 AM
Foundation Question cplain Getting Started 1 06-08-2008 12:06 AM
Another foundation question mfiore Getting Started 27 06-01-2008 04:31 PM
foundation question stoneman Outdoor Kitchen Design 6 03-15-2008 05:27 AM
Foundation Question??? kibarn Pompeii Oven Construction 8 12-23-2007 04:42 AM


All times are GMT -7. The time now is 10:02 PM.

Powered by vBulletin® Copyright ©2000 - 2014, Jelsoft Enterprises Ltd.
Search Engine Friendly URLs by vBSEO 3.6.0
2006/10 Forno Bravo, LLC