Default Entry arch form work

Hi. Laid the bricks for the entry arch today. How long should I wait before I remove the form work?

Also what is the best method to clean the bricks once they are laid?

Cheers
Jase
Reply With Quote
  #2  
Old 10-05-2008, 10:26 AM
dmun's Avatar
Moderator
 
Join Date: Jul 2005
Location: New Jersey USA
Posts: 4,216
Default Re: Entry arch form work

Quote:
Also what is the best method to clean the bricks once they are laid?
If at all possible, clean the excess mortar off with water and a sponge about six hours after the days build. Getting mortar off once it's set gets more difficult.
__________________
My geodesic oven project:
To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts.
,
To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts.
Reply With Quote
  #3  
Old 10-06-2008, 04:01 AM
nissanneill's Avatar
Il Pizzaiolo
 
Join Date: Apr 2007
Location: Adelaide, South Australia
Posts: 1,845
Thumbs up Re: Entry arch form work

Jase,
if you mixed your mortar correctly and not too wet and you wet your bricks prior to laying (they then don't suck excess moisture from your mortar), then I would remove the formwork within at least a couple of hours of laying. The bricks should be self supporting and provided you have sufficient buffering on the sides, then they should be self supporting as soon as the mortar stiffens up, even before it sets properly.
This as Dmun says, makes cleaning the bricks much easier.
You can always wash the finished bricks with a brick wash (which is diluted hydrochloric or pool acid, but use with extreme care as it bites! It also allows you to rake or roll your joints better.

Neill
__________________
Prevention is better than cure, - do it right the first time!

The more I learn, the more I realise how little I know


Neillís Pompeiii #1

To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts.

Neillís kitchen underway

To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts.
Reply With Quote
  #4  
Old 10-06-2008, 04:01 PM
Laborer
 
Join Date: May 2008
Location: Howden, Tasmania, Australia
Posts: 62
Default Re: Entry arch form work

Thanks Neill. The mortar was like a sticky thick toothpaste, is that about right? and I did soak the bricks prior to laying them.

It reminded me of the clay I used to use in when I was doing pottery at high school so many years ago.

Cheers
Jase
Reply With Quote
  #5  
Old 10-07-2008, 01:32 AM
nissanneill's Avatar
Il Pizzaiolo
 
Join Date: Apr 2007
Location: Adelaide, South Australia
Posts: 1,845
Thumbs up Re: Entry arch form work

Sounds just about ideal, stiff but sticky!
You did the right thing by wetting your bricks so they don't absorb too much water from the mortar which weakens it or mainly the bond a little.

Neill
__________________
Prevention is better than cure, - do it right the first time!

The more I learn, the more I realise how little I know


Neillís Pompeiii #1

To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts.

Neillís kitchen underway

To view links or images in signatures your post count must be 0 or greater. You currently have 0 posts.
Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Drake's 38" Oven DrakeRemoray Pompeii Oven Construction 119 01-11-2013 01:31 AM
Lighting the entry arch?? woods witch Pompeii Oven Construction 0 08-28-2008 04:28 AM
Entry arch Xabia Jim Design Styles, Chimneys and Finish 5 07-15-2008 08:03 AM
Styrofoam Form for the vent arch? thebadger Pompeii Oven Construction 10 04-13-2008 06:03 PM
brick thickness for top of landing arch waynebergman Pompeii Oven Construction 2 11-28-2007 09:29 AM


All times are GMT -7. The time now is 02:52 AM.

Powered by vBulletin® Copyright ©2000 - 2014, Jelsoft Enterprises Ltd.
Search Engine Friendly URLs by vBSEO 3.6.0
© 2006/10 Forno Bravo, LLC