Go Back   Forno Bravo Forum: The Wood-Fired Oven Community > Pizza Oven Design and Installation > Tools, Tips and Techniques

Reply
 
LinkBack Thread Tools Display Modes
  #1  
Old 05-08-2013, 07:56 AM
Serf
 
Join Date: Apr 2008
Location: western new york
Posts: 6
Default Partially fill joint between dome fire bricks with steel wool before refractory

Doing a little maintenance on my 5 year old WFO (built from Alan Scott's book). One of the joints between dome fire bricks has lost its refractory mortar (Heat Stop).

I tried to fill it with refractory mortar, but it was too deep, and the
mortar fell out.

I think if I partially filled the joint with something like steel wool(or some
other recommended material) it would form a base that I could finish with Heat Stop.

Anyone have any experience with this problem or any ideas that might help withthe repair.

Thanks in advance.
Reply With Quote
  #2  
Old 05-08-2013, 08:28 AM
Tscarborough's Avatar
Il Pizzaiolo
 
Join Date: Oct 2009
Location: Ausitn
Posts: 3,108
Default Re: Partially fill joint between dome fire bricks with steel wool before refractory

The deeper the better. Mix some heatstop and put it in a heavy duty ziplock bag. Cut one corner out so that it is about the size of the crack and squeeze it in. You may have to make the mix a tad wetter than normal.
Reply With Quote
  #3  
Old 05-08-2013, 01:14 PM
david s's Avatar
Il Pizzaiolo
 
Join Date: Mar 2007
Location: Townsville, Nth Queensland,Australia
Posts: 4,824
Default Re: Partially fill joint between dome fire bricks with steel wool before refractory

Filling cracks is usually not particularly successful, but you can improve the success rate with this method.
1. Take some of your Heatstop and sieve out the aggregate.

2. Wet the area to be filled and leave for 10 mins so it is damp not wet.

3. Mix some water with the sieved heatstop to form a thin slurry and paint this into the area to be filled. Then wait 10 mins again to allow the stuff to penetrate into the cracked surfaces.

4. Mix up some unsieved Heatstop to a peanut butter consistency and apply.

5. Leave for a few days before refiring.

This method creates a better bond with the surfaces to be filled. Calcium aluminate cements do not require the extended curing times like Portland cement. 24 hrs and it's done, but you do need to then wait until it's properly dry.

Last edited by david s; 05-08-2013 at 01:20 PM.
Reply With Quote
  #4  
Old 05-11-2013, 07:34 AM
Serf
 
Join Date: Apr 2008
Location: western new york
Posts: 6
Default Re: Partially fill joint between dome fire bricks with steel wool before refractory

Thanks for your replies. I will incorporate both methods and give it a try. The joint in question is a mortar joint between two fire bricks in the dome.

thanks again
Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Steel Dome Oven Wiley Other Oven Types 195 01-14-2014 11:06 PM
Oven (Floor - Wall - Dome) Fire Bricks Thickness?! southpaw Pompeii Oven Construction 11 03-12-2011 10:54 AM
Steel in oven dome? maburton Pompeii Oven Construction 8 05-04-2008 05:29 AM
Fire Mortar vs. Refax Refractory Mortar southpaw Pompeii Oven Construction 4 04-07-2007 05:02 AM
How many fire bricks for a 32" oven? Fio Pompeii Oven Construction 1 05-16-2006 05:32 AM