#1  
Old 04-04-2007, 06:04 AM
Journeyman
 
Join Date: Oct 2006
Location: Adelaide, Australia
Posts: 257
Default Hendo's Oven

Time to start posting some photo’s of my brick oven construction. I originally proposed to build a stand-alone unit, complete with gabled tiled roof, like so many I have seen in Italian backyards. But before I knew it, the project had increased to building an adjoining gazebo, and then still more to incorporate an outdoor kitchen, complete with sink, bar fridge, barbecue and deep fryer.

The first photo gives a perspective of the construction site, with excavations for the oven & bench footings and trench for gas & water supplies and storm water pipes already completed. The area next to the back fence has been levelled for the gazebo and aggregate dumped for the slate paving. The mess has truly begun!



The next two photo’s show details of the footing excavations. I opted to go for the same footings as specified for our house extensions some years back, as they will have to support a similar weight in our highly reactive clay soil. Probably overkill, but time will tell. The main footing is 14” wide by 36” deep, and reinforcement is by 6 ⅝” bars (3 top 3 bottom).



Reply With Quote
  #2  
Old 04-04-2007, 06:09 AM
Journeyman
 
Join Date: Oct 2006
Location: Adelaide, Australia
Posts: 257
Default Re: Hendo's Oven

The excavations lined with plastic membrane, and formwork and reinforcing steel mostly installed. Unfortunately, due to the slope of the land, the footing was stepped down by three brick courses (10”) from the oven slab to the gazebo floor, effectively lowering the hearth slab on the uphill side by the same amount. Less height to store wood for the fire – darn! I was really depending on 4 block courses to enable good access for the wood storage area under the hearth slab.





The cavernous excavations took over 6 yards of concrete to fill! And of course it started raining half-way through.



Reply With Quote
  #3  
Old 04-04-2007, 06:11 AM
Journeyman
 
Join Date: Oct 2006
Location: Adelaide, Australia
Posts: 257
Default Re: Hendo's Oven

Oven slab and beam floated off, and looking a bit on the wet side, due to the rain.





Next day, the formwork was removed …



Reply With Quote
  #4  
Old 04-04-2007, 06:13 AM
Journeyman
 
Join Date: Oct 2006
Location: Adelaide, Australia
Posts: 257
Default Re: Hendo's Oven

… and the rubble for the pavers spread and compacted. Holes were dug for the gazebo posts.





Gazebo structural elements installed, and a 1” copper gas line for the barbecue laid in a trench dug around the oven slab.


Reply With Quote
  #5  
Old 04-04-2007, 06:16 AM
Journeyman
 
Join Date: Oct 2006
Location: Adelaide, Australia
Posts: 257
Default Re: Hendo's Oven

Electric cables installed and pavers laid, together with corrugated steel roof & guttering, and blue board cement sheet fixed to the structural stud-work next to the fence. Apart from some lattice and a textured surface applied to the blue board, the gazebo structure is largely finished.



Now on with the hearth stand! The footprint of the concrete support blocks is marked out …



and the first course mortared in place.

Reply With Quote
  #6  
Old 04-04-2007, 06:19 AM
Journeyman
 
Join Date: Oct 2006
Location: Adelaide, Australia
Posts: 257
Default Re: Hendo's Oven

The blocks are designed to interlock with adjacent blocks and the course above, so once the first course has been laid in mortar (to compensate for any unevenness in the slab), the remaining courses are dry laid. Mortar thickness varied from Ό” at one corner to a little over Ύ” at the opposite corner, so the slab was reasonably level. The blocks are 8” high and are bevelled on the sides and top, to simulate a ½” mortar joint. Laying these blocks was very satisfying work, as it all goes up so quickly!





Midway through construction of the hearth stand, I decided to use ribbed steel decking, instead of the usual plywood formwork, to support the hearth slab. This is used extensively in the building industry for multi-story buildings, and supports the concrete slab - both physically and structurally. I used 1mm thick galvanised steel, which is able to span over 2 metres (6’ 6”) in a single span for the 5” slab thickness that I ended up with (my span is less than 4’).

At around the same time, I decided to change from 4” vermiculite concrete to 2” Calcium Silicate boards for my sub-dome insulation layer, with the result that I could increase the height of my hearth slab to accommodate more wood, and make it a bit easier to retrieve. The down side was that each block of the top course of concrete blocks had to be cut to 3” high. I achieved this by way of a diamond blade in my 5” angle grinder, and it was fairly straight forward, if a bit dusty! The internal webs of the blocks were drilled as much as I could from each end, then the block split quite easily. In this way, I successfully managed to get two ⅜-height blocks out of each whole block. I made sure that the overall height of the blocks was the same as a whole number of brick courses, because the steel decking for the vent landing would be supported by brickwork at the oven entrance – part of the brick bench structure in the gazebo.

Reply With Quote
  #7  
Old 04-04-2007, 06:21 AM
Journeyman
 
Join Date: Oct 2006
Location: Adelaide, Australia
Posts: 257
Default Re: Hendo's Oven

I also put in some U-shaped ½” rebar down four of the cores and across the top of the steel decking, and held these in place with some scrap timber pieces while the cores were being filled. I had a mate help me with filling the cores, and we rodded each core thoroughly (with ½” rebar with a bullet-shaped tip) after filling with ready-mix concrete. I ensured that the cores were thoroughly moist before filling with concrete, but even so, the blocks sucked a huge amount of moisture out of the concrete and rodding was difficult.



Reply With Quote
  #8  
Old 04-04-2007, 06:22 AM
Journeyman
 
Join Date: Oct 2006
Location: Adelaide, Australia
Posts: 257
Default Re: Hendo's Oven

Then, on to the brickwork for the bench. After the walls were marked out, the bricklayer got laying! In a few hours, he had finished all the brickwork needed to put in the last piece of steel decking and construct the formwork for the hearth slab. The brick walls will both support the bench top and act as dividers between (from left) the sink cupboard, bar fridge, ash pit, barbecue/wood storage and deep fryer with cupboard below.







Reply With Quote
  #9  
Old 04-04-2007, 06:24 AM
Journeyman
 
Join Date: Oct 2006
Location: Adelaide, Australia
Posts: 257
Default Re: Hendo's Oven

Another afterthought, motivated by other members’ experiences was to install some thermocouples to measure hearth temperature, both near the surface of the cooking floor, and at the junction between the floor and sub-dome insulation layer. As I could obtain only a six way selector switch for the digital temperature display, I opted to put four of the thermocouples in the cooking floor, and two in the dome. I wanted to ensure I could replace a thermocouple with a minimum of fuss (if I ever needed to), so I decided to make up some thermocouple housings which could be fixed to the steel decking. An instrument supply company provided 4 thermowells which had been made to the desired length, and I fixed these to cheap stainless steel mugs via a brass bush and back nut.



The ⅛" diameter thermocouple probes will be fastened inside each thermowell by means of a ¼" compression fitting, accessible from under the slab.


Last edited by Hendo; 06-27-2007 at 08:04 PM. Reason: Probe diameter amended (from ¼")
Reply With Quote
  #10  
Old 04-04-2007, 06:26 AM
Journeyman
 
Join Date: Oct 2006
Location: Adelaide, Australia
Posts: 257
Default Re: Hendo's Oven

The completed assemblies were then fixed in position with silicon sealant to the steel decking which had had 3” holes cut through it with a hole saw. Each assembly was connected to metal conduits (old ½” water pipe) with silicon, after a draw wire had been threaded through the pipes. These days, galvanised water pipe is unheard of in the plumbing industry, so I had a devil of a time trying to find a pipe threader to connect all the fittings! All the pipes terminate at a convenient height above the future bench top where the switch and temperature display will be mounted in a brick wall.





Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On


Similar Threads
Thread Thread Starter Forum Replies Last Post
Oven Curing james Firing Your Oven 324 04-13-2014 05:31 PM
Why Italian Wood-Fired Ovens are Round james Newbie Forum 50 04-01-2014 09:14 PM
Tuscan and Naples designs james Pompeii Oven Construction 5 09-11-2011 04:53 PM
Mediocre Pie weekend/Why were my pies all “dough-y?” Fio Pizza 11 03-25-2010 06:29 AM
All things being equal Lester Newbie Forum 13 12-21-2009 01:26 AM


All times are GMT -7. The time now is 03:44 AM.

Powered by vBulletin® Copyright ©2000 - 2014, Jelsoft Enterprises Ltd.
Search Engine Friendly URLs by vBSEO 3.6.0
© 2006/10 Forno Bravo, LLC