stchang 09-24-2008 04:35 PM

Chimney Construction question
 
Hi again,

I got the 4 dome pieces aligned correctly, and now had a question about the 2 chimney pieces.

Do I put refrax between each other and the dome?

Also the piece with the 2 bumps. Do the bumps go in front or the back?

Steve

james 09-24-2008 06:11 PM

Re: Chimney Construction question
 
2 Attachment(s)
Hi Steve,

You are making good progress. The vent piece with the rectangular opening goes on first, with the bumps to the front and the front of the vent lined up with the front (vent area walls) of the oven. I am attaching a couple of photos.

Yes, used Refmix between each layer (oven to vent, vent to round chimney adapter), and use a little Refmix on the outside of the seams to ensure that you have an airtight seal.

Keep going!
James