You don't need the sonotuble below the visible part. Unless the hole is caving in on you, just can just fill it directly with concrete.
Reply With Quote
  #22  
Old 06-02-2009, 06:03 PM
Serf
 
Join Date: Mar 2008
Location: NorthEast
Posts: 21
Default Re: Started digging, stopped digging. Water problems.

Quote:
Originally Posted by Neil2 View Post
You don't need the sonotuble below the visible part. Unless the hole is caving in on you, just can just fill it directly with concrete.
Are you in the right thread sir? I'm not sure if we were asking / talking / mesmerizing about sonotubles......

But of course you are welcome here. We all are. 'Cuz we're cool like that.
Reply With Quote
  #23  
Old 06-09-2009, 08:36 AM
Serf
 
Join Date: Mar 2008
Location: NorthEast
Posts: 21
Default Minor Progress over last weekend

Some of the platform pour floor is in, steel just laid over the top to see if we have enough. Still deciding if we'll be pouring a ledge over the front etc before the outside form gets built. Bricks stacked in front to get the visual.

Reply With Quote
Reply

Thread Tools
Display Modes

Posting Rules
You may not post new threads
You may not post replies
You may not post attachments
You may not edit your posts

BB code is On
Smilies are On
[IMG] code is On
HTML code is Off
Trackbacks are On
Pingbacks are On
Refbacks are On



All times are GMT -7. The time now is 06:43 PM.

Powered by vBulletin® Copyright ©2000 - 2014, Jelsoft Enterprises Ltd.
Search Engine Friendly URLs by vBSEO 3.6.0
2006/10 Forno Bravo, LLC