web analytics
5" foundation = 3in gravel + concrete? - Forno Bravo Forum: The Wood-Fired Oven Community



Forno Bravo Forum Thread Message

Hello, Forno Bravo Community Forum Members!

The Forno Bravo team has heard the feedback in regards to the community forum. We wanted to take the time to re-enforce our commitment to a fully engaged Forum with professional moderation.

Our top priority as a company is to fix all forum errors and issues that you are experiencing. As we are swiftly working on these problems, we want to say that we highly value the Forum Bravo Community Forum and every single community forum member.

We have set up this thread so that every member can address any concerns, issues and questions about the forum. Please feel free to ask whatever you would like in regards to the forum; let us know what issues you are experiencing so we can work on resolving them as fast as possible. However, we stress that we would like constructive engagement, so please be specific about the issue you are experiencing.

Thank you for all of your patience and continued support.

Link to topic: http://www.fornobravo.com/community/...with-new-forum
See more
See less

5" foundation = 3in gravel + concrete?

  • Filter
  • Time
  • Show
Clear All
new posts

  • 5" foundation = 3in gravel + concrete?

    am planning out a Casa 2g 90 build, will be laying my first foundation.

    When the install guide says 5 1/2 slab, then goes on to say 3" gravel to start with plastic on top, does that mean excavate 8 1/2" do the 3" gravel, then do a full 5 1/2 slab? or is the 3" included in the 5 1/2"? I'm guessing its total 8 1/2" slab, but not clear and I dont know better, and I dont want to mess this part up!

    other questions:
    -how to estimate how much concrete is needed?
    -looking at the corner install plan they have in the manual, how much bigger does the foundation need to be?



  • #2
    Re: 5" foundation = 3in gravel + concrete?

    "does that mean excavate 8 1/2" do the 3" gravel, then do a full 5 1/2 slab?"


    Measure your slab in cubic feet. For example a 6 ft by 6ft by 5 1/2 inch slab = 16.5 cubic feet, or about .6 cubic yards.

    If you are going the pre-mix bag route, there is 0.6 cubic feet in one 80 pound bag. Therefore the slab will require 16.5/.6 = 28 bags. Get more than you need , you can always return un-opened bags.


    • #3
      Re: 5" foundation = 3in gravel + concrete?

      thanks for that info... I started my excavation today, assuming that I needed 3" gravel then 5 1/2 in slab.