We have received feedback regarding recent issues with page loading response time. We believe the slow response issue stems from the analytics we added with the new Forum. We are in the process of reconfiguring those elements and, after an approximate 24-hour time period for the reconfiguration to run, we anticipate a return to normal page load times. Thank you for your patience!
2 of 3 < >


Hello, Forno Bravo Community Forum members.

As many may have noticed already, the Community Forum site was briefly down today. While working on scheduled routine maintenance, we encountered an error when trying to add a software update. As the site is now back up and running, some of you may notice that some recent data has been misplaced from November 10th up to today. We are currently working on resolving the issue. The forum has full operational capabilities and we encourage all forum members to continue actively posting in the threads.

We apologize for any inconvenience that this issue may have caused you. The Forno Bravo family values each and every member of our community. If you have any issues or concerns, please feel free to let us know on our issues thread here:


Thank you for understanding.
3 of 3 < >

Forno Bravo Forum Thread Message

Hello, Forno Bravo Community Forum Members!

The Forno Bravo team has heard the feedback in regards to the community forum. We wanted to take the time to re-enforce our commitment to a fully engaged Forum with professional moderation.

Our top priority as a company is to fix all forum errors and issues that you are experiencing. As we are swiftly working on these problems, we want to say that we highly value the Forum Bravo Community Forum and every single community forum member.

We have set up this thread so that every member can address any concerns, issues and questions about the forum. Please feel free to ask whatever you would like in regards to the forum; let us know what issues you are experiencing so we can work on resolving them as fast as possible. However, we stress that we would like constructive engagement, so please be specific about the issue you are experiencing.

Thank you for all of your patience and continued support.

Link to topic: http://www.fornobravo.com/community/...with-new-forum
See more
See less

New Vault Style oven start

  • Filter
  • Time
  • Show
Clear All
new posts

  • New Vault Style oven start

    I'm definitely in the category of "needing all the help I can get", and thick skinned, so fire away!

    I'm new to this building thing and I know it shows :-)

    I should mention, this will be a "commercial" oven - we're baking bread for sale. So appearances are not our most important consideration.

    I would like to build the largest oven that will fit on this 5 foot x 6 foot base.

    And I'm getting nervous as I get to the actual brick work!

    Here is the base forms built...
    Attached Files

  • #2
    Re: New Vault Style oven start

    I should clarify, the block base is 5 x6 feet, not the slab.

    I did wonder if i could have used mortar on the first row of block, then dry stacked the rest. I filled about 80% of the block holes with rebar and cement and would have happily filled the remainder if it would have saved me the trouble of trying (largely unsuccessfully) to learn how to mortar those blocks.

    Of course, the layer with the angle iron would have to be mortared too I guess, in order to compensate for the thickness of it.

    I ended up with way too thin layers of mortar anyway. I'm hoping the strength will be compensated with the holes filled.
    Attached Files


    • #3
      Re: New Vault Style oven start

      My lack of mortaring skills are pretty evident here :-)

      But overall, I'm OK with how things are turning out. Having extremely low expectations has its rewards.
      Attached Files


      • #4
        Re: New Vault Style oven start

        The 3/4 inch plywood is on and fairly level. I bent the rebar with a couple 8 foot lengths of 1/2 inch galvanized pipe propped up between the twin trunks of a walnut tree. It worked well for getting sharp angles in the short pieces needed for the front row of blocks.
        Attached Files


        • #5
          Re: New Vault Style oven start

          Here the rebar is more or less in place. I straightened it up while adding the cement. It seemed to stick up higher than I thought it would, but I planned to pour a 5 inch slab anyway, so I didn't mess with it too much.
          Attached Files


          • #6
            Re: New Vault Style oven start

            Looks like a great start!
            Picasa web album
            Oven-building thread


            • #7
              Re: New Vault Style oven start

              This is how the rebar worked for me.

              I have the forms on in the second photo, rifle just happened to be there but it works to provide scale.
              Attached Files


              • #8
                Re: New Vault Style oven start

                I hope this isn't a duplicate post -

                Here is a shot of the block holes filled. I filled each of the 3 holes on each corner, all the holes across the front and at least every other hole along the back and sides.

                I didn't stuff the holes with used cement bags, so they are solid to the ground and with a rebar. I hope that provides enough support.

                I screed the slab with a too short 2x4 so its a bit rough too, but I'm not concerned about that. I just hope it doesn't collapse ;-)
                Attached Files